Temporary Road Closures & Construction

Full Road Rehabilitiation Projects

Portions of Beechwood Road have been identified as requiring rehabilitation. These sections are located between County Road 1 and Drive-In Road, as well as Johnson Sideroad to Deseronto Road.  The road will be pulverized back to a gravel state, with additional gravel added. This will be followed by an application of Surface Treatment over the entire road.  Preparation work, including tree clearing, ditching, culvert replacements, grading, and granular applications will be completed by Town forces. A contractor will complete the pulverization and surface treatment portions of the work.
  • Start Date: May 1st, 2026
  • End Date: June 30th, 2026
Traffic will be reduced to alternating single lane closures for the duration of the project. Traffic construction signs will be installed. Drivers and pedestrians are required to obey all construction signs and expect delays. 
This project has been funded in part by the Ontario Community Infrastructure Fund (OCIF). 

Homestead Road has been identified in the Roads Need Study as requiring rehabilitation.  The road will be pulverized back to a gravel state, with additional gravel added. This will be followed by an application of Surface Treatment over the entire road.  The preparation work (trees, ditching, and culverts) will be performed by Town forces, and a contractor will perform the pulverization and surface treatment applications.
  • Start Date: April 1st, 2026
  • End Date: August 15th, 2026
Traffic will be reduced to alternating single lane closures for the duration of the project. Traffic construction signs will be installed. Drivers and pedestrians are required to obey all construction signs and expect delays.
This project has been funded in part by the Ontario Community Infrastructure Fund (OCIF). 

A portion of Old Hamburg Road, Champlain Street, and Old Kingston Road were affected by construction activities last year due to the servicing of utilities to the new housing development be constructed along Old Hamburg Rd and Champlain St. Due to some outstanding construction efforts still remaining within the road allowances of these roads, the surface was unable to be reapplied during the 2025 construction season. The remaining required construction activities are scheduled to be carried out during May and the first part of June, in order to reapply surface treatment around mid-June. 
  • Start Date: May 1st, 2026
  • End Date: July 15th, 2026
Traffic will be reduced to alternating single lane closures for the duration of the project. Traffic construction signs will be installed. Drivers and pedestrians are required to obey all construction signs and expect delays.
A portion of this project has been funded in part by the Canada Community Building Fund (CCBF). 

Single Surface Treatment Program

Work will begin on the rehabilitation of approximately 16.5 kms of surface treated roadways with localized surface repairs and application of a single surface treatment (chip seal).  These chip seals typically add 6 to 8 years of additional service life at a relatively low cost.  Rehabilitations also help lower unplanned maintenance costs (potholes, cracking and edge break up). 
  • Start Date: May 1st, 2026
  • End Date: August 15th, 2026
Traffic will be reduced to alternating single lane closures for the duration of the project. Traffic construction signs will be installed. Drivers and pedestrians are required to obey all construction signs and expect delays.
Portions of these projects have been funded in part by the Canada Community Building Fund (CCBF) and the Ontario Community Infrastructure Fund (OCIF).

Bridge Projects

Based on the last Biannual OSIM's inspection it was identified that the installation of a barrier system is required on the Manion Rd Bridge. This includes the procurement and installation of compliant steel beam guiderails and end treatments in accordance with current bridge safety standards.
  • Start Date: May 15th, 2026
  • End Date: June 15th, 2026
Traffic will be reduced to alternating single lane closures for the duration of the project. Traffic construction signs will be installed. Drivers and pedestrians are required to obey all construction signs and expect delays.
This project has been funded in part by the Canada Community Building Fund (CCBF). 

Based on the last Biannual OSIM's inspection it was identified that this structure requires descaling of the concrete coating that is applied to the underside of this bridge, as well as a more in depth inspection of the structure that would be carried out in conjunction to the descaling. This work will require lane closures and is estimated to take 2 nights to complete.
  • Start Date: June 1st, 2026
  • End Date: October 30th, 2026
Traffic will be reduced to alternating single lane closures for the duration of the project. Traffic construction signs will be installed. Drivers and pedestrians are required to obey all construction signs and expect delays.
This project has been funded in part by the Canada Community Building Fund (CCBF). 

Granular Resurfacing

Resurfacing adds a 4" layer of new granular material to restore the gravel road surface. Rebuilds the wearing course, improves drainage, and strengthens the road structure. Required when the existing surface has thinned, lost fines, or no longer holds shape. There is also some ppreliminary brushing, tree clearing, and ditching to be conducted prior to resurfacing.
  • Start Date: April 1st, 2026
  • End Date: June 15th, 2026
Traffic will be reduced to alternating single lane closures for the duration of the project. Traffic construction signs will be installed. Drivers and pedestrians are required to obey all construction signs and expect delays. 

If you require the short-term use of a municipal road and/or sidewalk you will need to obtain a temporary road closure permit from the Town. Permits are issued by the Public Works Department in accordance with Town By-law No. 2025-0032

As per Council policy, there is no application fee or barricade rental cost for temporary road closures associated with a Local Not-for-Profit Event. Applicant organizations will still be responsible for costs associated with: 

  • Staffing to supervise the road closure and road safety plan; 
  • Liability insurance; and 

  • Providing notice to businesses and residents within the closure area.  

Temporary Road Closure Applications can be completed through this form.

Road closures that are part of a community event, such as a race, parade, or festival, will also be required to submit a Community Event Application

Temporary road closures associated with construction or other commercial policies will also require a Municipal Easement Work Permit from the Public Works Department.  

Temporary road closures that involve a County road will also require approval from the County of Lennox and Addington. If your requested road closure includes a County road, Town staff will forward your application and contact information on to County staff.  

For permanent road closure applications, visit our Municipal Land Sales page.

Sign up for Newsroom Updates

Stay up to date on the Town of Greater Napanee's activities, events, programs, and operations by subscribing to our Newsroom.